Construction waste management plans in Ireland: a guide to RWMPs

In Ireland, a construction or demolition project’s waste plan is called a Resource & Waste Management Plan (RWMP). It is prepared under the EPA’s Best Practice Guidelines for the Preparation of Resource & Waste Management Plans for Construction & Demolition Projects (2021), which replaced the 2006 guidelines. It’s usually submitted with the planning application and kept up to date throughout the build.

If you’ve searched for a “site waste management plan”, that’s the UK term. Irish planning authorities ask for an RWMP.

Do you need a Tier 1 or Tier 2 RWMP?

The level of detail depends on the size of the project. Projects below all of these thresholds can usually use a simpler Tier 1 plan:

Project type
Tier 1 if below
New residential 10 dwellings
Residential retrofit 20 dwellings (or fewer)
New commercial, industrial, institutional, educational, health and other buildings 1,250 m² aggregate floor area
Retrofit of those buildings 2,000 m² aggregate floor area
Demolition 100 m³ of C&D waste in total

Anything above these thresholds, plus large infrastructure projects (road, rail, gas, energy), is a Tier 2 project and needs a bespoke RWMP that follows the full EPA guidelines. Some councils, such as Limerick, publish their own Tier 1 template. Always check with your local authority.

What goes in a resource and waste management plan

  1. Project details: planning reference, contractor, site manager and a named Resource Manager.
  2. Design-stage measures: how waste is designed out, e.g. ordering timber and plasterboard to length, reusable hoarding.
  3. Resource inventory: expected quantities of concrete, brick, timber, metals, soil and stone, and how much will be prevented or reused.
  4. Waste inventory: expected tonnes per waste type, by List of Waste (LoW/EWC) code, split into recycled, recovered and disposed.
  5. Authorised collectors and facilities: the NWCPO permit number of each waste collector and the permit of each receiving site.
  6. Hazardous waste: how asbestos, contaminated soil and other hazardous materials will be handled by authorised operators.
  7. Record-keeping: dockets and records of every load leaving site. Councils advise keeping them for at least seven years.

Common C&D waste codes

Material
LoW / EWC code
Concrete 17 01 01
Bricks 17 01 02
Mixed concrete, bricks, tiles 17 01 07
Wood 17 02 01
Plastic 17 02 03
Iron and steel 17 04 05
Mixed metals 17 04 07
Soil and stone (clean) 17 05 04
Plasterboard / gypsum 17 08 02
Mixed C&D waste 17 09 04
Construction materials containing asbestos (hazardous) 17 06 05*

What is inert waste?

Inert waste is waste that doesn’t break down, burn, dissolve or react in any significant way, so it won’t pollute water or harm the environment around it. On a building site that means clean concrete, brick, tiles, ceramics, stone and uncontaminated soil. Inert waste is the easiest C&D waste to recycle, often as crushed aggregate. Mix it with timber, plastic or plasterboard and it stops being inert, and costs more to deal with.

Two Irish routes matter for inert material. Clean soil and stone can be declared a by-product to the EPA (Regulation 27) instead of a waste. And under the EPA’s end-of-waste decision for recycled aggregates, crushed concrete can stop being classed as waste if it meets the criteria.

How Greyhound supports your RWMP

  • Authorised collector: NWCPO permits NWCPO-14-11447-06 and NWCPO-21-12653-01, for your plan’s collector section
  • Segregated skips and RoRos on site for inert, timber, metal and mixed C&D streams
  • Full audit trail through our Elemos customer portal, with tonnages by waste stream for your waste inventory and close-out report
  • Over 98% of material we receive is recycled
  • Onsite waste segregation training for site crews

FAQ

Is a site waste management plan the same as an RWMP?

They cover the same ground, but “site waste management plan” is the UK term. In Ireland you prepare a Resource & Waste Management Plan under the EPA’s 2021 guidelines.

When is an RWMP submitted?

Usually with the planning application. It is then updated as the project moves from design into construction.

Who writes the RWMP?

The developer or contractor, often with an environmental consultant. A named Resource Manager is responsible for keeping it up to date.

Is soil and stone inert waste?

Clean, uncontaminated soil and stone is. Soil contaminated with hazardous substances is hazardous waste (code 17 05 03*).

What records do I need to keep?

A record of every load: material, quantity, date, the authorised collector and the destination facility.